W-2

  1. Accomplishments: the PCB shield design has been completed and ordered. The board has been manufactured and is on its way. Components for said PCB have also been ordered.

  2. No feedback to integrate this week.

  3. No lessons learned this week.

  4. Next week:

    • (While awaiting PCB): start working on an early strap that attaches to the TrinketM0 so electronics can be properly tested soon after arrival, practice surface mount soldering.

    • (After PCB arrival): solder components and test the completed electronics assembly. If time allows, begin the preliminary CAD design for a main case.